The Gate is a 21-storey aparthotel in East London, comprising 178 serviced apartments and operated by Portland Brown.
Situated on Commercial Road — a red route and key arterial road into London — the development includes a two-storey basement extending across the full site footprint.
To enable the successful delivery of the 21-storey structure, the project team devised an innovative solution that allowed the traditional masonry façade to be constructed without the use of external scaffolding.
A pioneering climbing shroud was employed, marking only its second application in the UK, to provide external access for the installation of windows and brickwork up to the 21st floor. As the shroud ascends, it reveals a completed building envelope, allowing internal fit-out works to commence immediately within the apartments behind.
The use of the climbing shroud required meticulous coordination, as each element of the building envelope had to be fully completed prior to the shroud being raised. To reduce the risk of supply chain disruption, façade materials were procured in advance and stored at dedicated off-site facilities, enabling just-in-time delivery to site.
Ardmore’s proactive, solutions-driven approach delivered significant programme efficiencies by eliminating the need to dismantle external scaffolding once the envelope was complete — a process that can typically take up to 21 weeks.
Mechanical Infrastructure and Fit-Out Package including Energy Centre
Jul 2018 – Nov 2019
Ardmore Construction Ltd
Integrated into the Ardmore Group’s team & SHW Design
£ 2,732,000
41 White Church Lane, London, E1 7QR








We worked on this project together with Reef Group.